Access and scheduling
Pick the last Sunday in the old building first, then work backward. Your contractor usually needs the Monday after that service to pull pew fasteners, and an organ builder may need weeks rather than days, so both dates go on the plan before the truck does. Weekday loading has to leave the lot clear for funerals and the preschool or recovery groups many churches host, so tell us what is booked. If weekdays are full, ask about a Saturday or an evening start.
At the new building, confirm the sanctuary floor is finished and the pew layout is marked. A congregation leaving a leased storefront or a rented school gym for its own building often has one wide door and a long carry to the worship room, so we measure pew lengths against that route. From November through March, a snowfall can close a church lot on the weekend you picked, so hold a second date.